in NREGS and
make it a mass movement – district Hoshiarpur
To provide a framework for conceptualization and action, the following focal issues related to innovation,
change and especially to build a
firm rapport so as to motivate rural male and female members and also to
activate institutions like Panchayats and other rural
development agencies under NREGS are presented.
The Deputy Commissioner (Shri Megh Raj, IAS), Hoshiarpur assumed
the charge of Deputy Commissioner-cum-District Programme
Coordinator(NREGS), Hoshiarpur on
11.6.2009 and initiated the following steps :-
1) Integration of
Literacy with NREGA to make it a Mass Movement
On
joining as Deputy Commissioner,Hoshiarpur on 11.6.2009, it was observed that in
district Hoshiarpur although
NREGA scheme was launched on
2.2.2006 yet to look
after
the work in villages, no
Gram Rozgar Sewaks were appointed. However, the services
of Literacy workers had been taken to do additional work for which
it
was
decided to pay an honorarium of Rs.700/- per month to such workers. This was reviewed
in July, 2009 and it came to notice that the Continuing Education Scheme under the Literacy Programme
had since been closed
and the services of
all such literacy
workers terminated. Honorarium of
Rs.700/- p.m was
too meager an amount for
the duties assigned to
implement NREGA in its true spirit. After due
deliberations,, it was decided to
utilize the services
of Literacy workers, wherever they were willing by making their job cards and employing them as
Mates under Para 6.5.5
of NREGS guidelines. Accordingly, necessary
instructions were issued to
all Programme Officers that priority should be given to the Literacy workers for appointment as Mates
as they have
already been working
under NREGA and trained
to undertake this job. As on 24.9.2009, 740 Literacy workers
are functioning under NREGS as
Mates. A separate set of instructions is
being
issued
to these Literacy-cum-NREGA workers to impart
Literacy skills and create awareness about various Govt. programmes and policies
i.e. National Rural Health Mission, Nirmal Gram, Indira Awaas Yojana, Sarv Shiksha Abhyan, Public Distribution System, Swarnjayanti Gram Swarozgar Yojana, Prime Ministry Gram Sarak Yojana, Agricultural Technology Management Agency
(ATMA), World Bank assisted Water Supply programme etc.
during the lunch
break.
2)
Constitution of Monitoring Committees :-
During the meeting held on 19.8.2009, it was decided that a team consisting of Senior Officer alongwith one Technical Officer shall be constituted for each block for checking the development works especially for
NREGS and start an awareness programme about all Govt. programmes such as National Rural Health Mission, Sarv Shiksha Abhian, Nirmal Gram, Provision of
essential commodities under Public
Distribution System and world
bank assisted programme of providing potable drinking
water. These officers shall report about the checking of works
regularly
|
S. No |
Name of Officer |
Technical Officer attached |
Name of Block |
|
1 |
Sh.
Megh Raj, IAS, Deputy
Commissioner, Hoshiarpur |
Sh. Rejinder Kumar,
SDO, c/o XEN. Central works
Div, PWD(B&R), Hoshiarpur |
Bhunga |
|
2 |
Sh.Parmod Ban, IPS, Senior Superintendent of Police,
Hoshiarpur |
S.D.O.(Panchayati Raj),
Hoshiarpur |
Tanda
|
|
3 |
Smt. Kavita Singh, IAS,
Addl. Deputy Commissioner(Gen), Hoshiarpur |
Sh. Arjan Dev., SDO c/o XEN.
PWD(B&R)mDiv,No.2, Hoshiarpur |
Hoshiarpur-II |
|
4 |
Sh.
D.R. Bhagat, Addl. Deputy
Commissioner(Dev),Hoshiarpur |
Sh. Jaspal Singh Saini, Asstt. Engineer,
PSTC, Mahilpur |
Mahilpur |
|
5 |
Sh.
Karnail Singh , PCS, Sub Divisional Magistrate,
Hoshiarpur |
Sh. Ram Dyal, SDO, PSTC,
Hoshiarpur |
Hoshiarpur-I |
|
6 |
Sh.
Rahul Guptaa, , PCS,
Sub Divisional Magistrate,
Dasuya |
SDO(PR), Dasuya
|
Dasuya
|
|
7 |
Sh.
Iqbal Singh Sandhu, ,
PCS, Sub Divisional Magistrate,
Garhshankar |
SDO(PR), Garhshankar |
Garhshankar |
|
8 |
Sh.
Mohammed Taib, IAS, Sub Divisional Magistrate,
Mukerian |
SDO(PR), Mukerian
|
Mukerian |
|
9 |
Sh.
Rajesh Kumar Verma, XEN (PR), Hoshiarpur |
Jatinder Mohan, SDO, c/o XEN. PWD(B&R), Mukerian |
Hajipur |
|
10 |
Sh.
Bhupinderjit Singh, D.,R.O., Hoshiarpur |
Sh.Harmel Lal, SDO, c/o XEN,
Investigation Div, Hoshiarpur |
Talwara |
3) Training:-
Training sessions have been held with the BDPOs, APOs and officials of line
departments to ensure clarity regarding the execution of works under NREGS. Interactive sessions have been organized in all the ten blocks with the Sarpanches to remove
their misgivings and
bring clarity and transparency in
the works undertaken under NREGS.
4) Issue of Job cards :-
Upto the end of 31.3.2009 as many as 45135 job cards were issued to the rural households who were willing to do manual work under NREGS and a target of 52000 job cards was set upto
31.3.2009. On assuming the charge, a campaign was launched in the 3rd week of
June, 2009 in the district and daily progress was
monitored. Now as on
5) Logistic Plan of
District Hoshiarpur :-
To
ensure regular checking of works in
the villages by the BDPOs / SEPOs / Junior Engineers / A.P.O.s,
a logistic Plan ( block-wise) has been prepared. With the implementation of this Plan,
there will be considerable improvement
in the quality of works executed under NREGS.
6) Setting up
of Technical Wing for checking the Estimates :-
Prior to
11th June, 2009, the
estimates of the works being
executed by the Gram Panchayats as
well as line departments were
prepared on CSR basis
and money released without
any technical screening / appraisal
in the office of the ADC(Dev). After assumption of charge on
11.6.2009, a technical wing headed by the Executive Engineer, Panchayati Raj, Hoshiarpur has been set up to check all the estimates received from blocks and
line departments, scrutinize and appraise
the same as per NREGS
guidelines and ensure its
execution accordingly.
This will help reduce contractors
profit in the estimates which is in
built in the CSR.
7)
Videography and
Photography of the projects
All the
BDPOs have been provided digital cameras in July, 2009 to ensure
that videography / photography is
done prior to the launching of projects, during the execution of projects
and after the completion of project
and to keep a record
thereof. It will
help ensure accountability and
transparency. It has also been directed to
convene meetings of
Gram Sabha before starting any work under NREGS and videograph the
proceedings.
8)
Implementation of MIS system at Block level :-
In order
to ensure better computerization of
data management under NREGS, Computer systems have been provided to all the BDPOs by this office alongwith
internet connectivity. Data
entry of Job cards, muster
rolls has already been started
online at the software of the Ministry of Rural Development. In
all the blocks, an Addl. Programme Officer, a
Junior Engineer and a Computer operator
have been provided in all
the blocks by making fresh recruitment
in the 3rd week
of Sept.,2009.
9)
Annual Action Plan for the next year 2010-11
For preparing the Annual Action Plan for the
next year 2010-11, as per the NREGS guidelines, field functionaries of Block
level i.e. Social Education and
Panchayat Officers, Panchayat
Officers / Assistant Engineers, Junior Engineers, and the Additional Programme Officer(NREGS) have been deputed to
identify the works to be executed in the Gram Panchayats. After the identification of works, the same will be approved by the Gram Sabha. In this
way the Annual Action Plan will be prepared in time and approved before
| Sr.No | Details | Rs.(in las.) |
|---|---|---|
| 1. | Opening balance as on 1.4.2009 | 56.84 |
| 2. | Balance amount with the Departments | 451.44 |
| 3. | Funds from Govt. of India (1st) | 795.12 |
| Funds from Govt. of India (2nd) | 466.67 | |
| 4. | Funds from State Govt. | 0 |
| 5. | Misc. receipt | 0 |
| 6. | Total available amount | 1770.37 |
| 7. |
Amount given to Panchayats & Line Deptts ( as on 22.9.2009 ) |
1755.64 |
| 8. | Balance on as on 22.9.2009 | 14.73 |
Funds released and utilised during the year 2009-10 ( Rs. in lacs )
|
S/No |
Block
/ Depott. |
OB
of 2008-09 with Deptt. |
Funds
released during
2009-10 (upto 22.9.09 |
Total funds
available for exp.upto
22.9.2009 (Tot of Col.3 +4) |
Funds
utilised during upto
22.9.2009 |
|
1 |
2 |
3 |
4 |
5 |
6 |
|
1 |
Hoshiarpur-I |
0 |
87.67 |
87.67 |
38.05 |
|
2 |
Hoshiarpur-II |
34.40 |
67.39 |
101.79 |
49.19 |
|
3 |
Bhunga |
81.30 |
106.80 |
188.10 |
74.65 |
|
4 |
Tanda |
36.50 |
135.63 |
172.13 |
120.77 |
|
5 |
Dasuya |
0 |
177.02 |
177.02 |
94.00 |
|
6 |
Mukerian |
175.0 |
43.50 |
218.50 |
153.20 |
|
7 |
Talwara |
56.75 |
87.00 |
143.75 |
90.00 |
|
8 |
Hajipur |
51.50 |
79.85 |
131.35 |
85.30 |
|
9 |
Mahilpur |
0 |
73.38 |
73.38 |
41.50 |
|
10 |
Garhshankar |
0 |
103.07 |
103.07 |
30.00 |
|
11 |
DFO, Garhshankar |
5.98 |
26.00 |
31.98 |
29.08 |
|
12 |
DFO, Dasuya |
3.51 |
52.00 |
55.51 |
47.05 |
|
13 |
DFO,Hoshiarpur |
6.50 |
81.00 |
87.50 |
80.00 |
|
14 |
DFO(Wild
Life) |
0 |
10.00 |
10.00 |
0 |
|
15 |
XEN.
Drainage |
0 |
100.00 |
100.00 |
73.03 |
|
16 |
|
0 |
65.97 |
65.97 |
59.15 |
|
17 |
Exp. on
Contingency |
0 |
7.92 |
7.92 |
7.92 |
|
|
Total
: |
451.44 |
1304.2 |
1755.64 |
1072.89 |
(2) Physical Progress :-
| Sr.No | Details | Number |
|---|---|---|
| 1. | Job cards issued( as on 31.8.2009) | 56435 |
| Job cards issued( as on 24.9.2009) | 58196 | |
| 2. | Employment demanded | 17759 |
| 3. | Employment provided | 17759 |
| 4. | Mandays generated | 5.23 lacs |
***